Jal Shakti | Consultation for Inter-Linking of Rivers

ad
Over 3.5 lakh Water Conservation Measures taken up in a single month as nationwide Jal Shakti Abhiyan
Over 3.5 lakh Water Conservation Measures taken up in a single month as nationwide Jal Shakti Abhiyan

Under the National Perspective Plan (NPP), the National Water Development Agency (NWDA) has identified 30 links (16 under Peninsular Component & 14 under Himalayan Component) for preparation of Feasibility Reports. Details and current status of the proposals for inter-State linking of rivers under the Inter Linking of Rivers (ILR) Programme is furnished at Annexure.

The Government is pursuing the interlinking of rivers (ILR) programme in a consultative manner and has accorded it priority. There is a structured mechanism for preparing work plan, fixing the targets, consultation with all stakeholders, reviewing of the progress etc. for ILR projects. Detailed Project Reports (DPRs) of link projects after completion, are sent to the concerned States and efforts are made by way of holding regular consultation meetings with the concerned States to build consensus on water sharing, etc.

A Special Committee on Interlinking of Rivers (SCILR) was constituted in September, 2014 to expedite execution of the inter-linking of rivers (ILR) projects. Nineteen meetings of the Special Committee have been held so far and its latest meeting was held on 12.11.2021. Further, a Task Force for Interlinking of Rivers was also constituted in April, 2015 to look into the issues relating to interlinking of rivers. Fifteen meetings of the Task Force have been held so far and the latest meeting was held on 22.10.2021.

 

This Information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written  reply in Lok Sabha today.

*****

 

AnnexurE

 

 

Details and status of the proposals for inter-State linking of rivers under the Inter Linking of Rivers Programme

 

 

S.

No

Name Rivers States concerned Status
Peninsular Component
1(a) Mahanadi (Manibhadra)–

Godavari (Dowlaiswaram) link

Mahanadi and Godavari Jharkhand, Madhya Pradesh, Chhattisgarh, Telangana,

Andhra Pradesh, Odisha,

Karnataka and Maharashtra

FR Completed.
1(b) Mahanadi (Bermul)–

Godavari (Dowlaiswaram) link

Mahanadi and Godavari do FR Completed.

Preparation of DPR

under progress.

2 Godavari(Inchampall)-Krishna(Pulichintala)

link

Godavari and Krishna Odisha, Madhya Pradesh,

Chhattisgarh, Telangana, Andhra Pradesh, Maharashtra

and Karnataka

FR Completed.
3 Godavari(Inchampalli)-Krishna (Nagarjunasagar) link Godavari and Krishna –do– FR Completed.
DPR

Completed.

4 Godavari(Polavaram)

– Krishna(Vijayawada) link

Godavari and Krishna –do– FR Completed.
5 Krishna(Almatti)

–Pennar link

Krishna and Pennar Telangana, Andhra Pradesh,Maharashtra and Karnataka FR Completed.
6 Krishna (Srisailam)–Pennar link Krishna and Pennar –do– FR Completed.
7 Krishna(Nagarjunasagar)-Pennar (Somasila) link Krishna and Pennar –do– FR Completed.
DPR Completed.
8 Pennar (Somasila)–Cauvery(Grand Anicut) link Pennar and Cauvery Andhra Pradesh, Karnataka, Tamil Nadu, Kerala and

Puducherry

FR Completed.
DPR Completed.
9 Cauvery (Kattalai)–Vaigai–Gundar link Cauvery, Vaigai

and

Gundar

Karnataka, Tamil Nadu,

Kerala and Puducherry

DPR Completed.
10 Ken–Betwa link Ken and Betwa Uttar Pradesh and Madhya Pradesh DPR (Phase – I, II & Comprehensive report) Completed. The Project is now under implementation.
11

(i)

Parbati – Kalisindh –Chambal link Parbati, Kalisindhand Chambal Madhya Pradesh,Uttar

Pradesh and Rajasthan requested

to be Consulted during consensus building)

FR Completed.
(ii) Parbati-Kuno-Sindh link Parbati, Kuno

and Sindh

Madhya Pradesh and

Rajasthan

PFR completed.
12 Par-Tapi-Narmada

link

Par, Tapi and

Narmada

Maharashtra and Gujarat DPR Completed.
13 Damanganga – Pinjal link Damanganga and Pinjal –do– DPR Completed.
14 Bedti-Varada link Bedti and Varada Maharashtra, Andhra

Pradesh and Karnataka

PFR Completed.

Draft DPR completed

15 Netravati – Hemavati link Netravati

and Hemavati

Karnataka, Tamil Nadu and Kerala PFR Completed.
16 Pamba – Achankovil –Vaippar link Pamba,Achankovil and Vaippar Kerala and Tamil Nadu FR Completed.
 

Integration of Eastern Rajasthan Canal Project of Rajasthan and Parbati – Kalisindh –

Chambal link.

 

Himalayan Component
1. Manas-Sankosh-Tista-Ganga(M-S-T-G)link Manas, Sankosh,

Tista and Ganga

BHUTAN & INDIA

(Assam,West Bengal and

Bihar)

FR completed.

DPR in progress.

2. Kosi-Ghaghra link Kosi and Ghaghra NEPAL & INDIA

(Bihar and Uttar Pradesh)

PFR completed
3. Gandak-Ganga link Gandak and

Ganga

–do– FR completed (Indian

portion)

4. Ghaghra-Yamuna link Ghaghra and

Yamuna

–do– FR completed (Indian

portion)

5. Sarda-Yamuna link Sarda and

Yamuna

NEPAL&INDIA

(Bihar, Uttar Pradesh,

Uttarakhand, Haryana

And Rajasthan)

FR completed (Indian

portion)

6. Yamuna-Rajasthan link Yamuna and Sukri Gujarat, Rajasthan, Haryana and UttarPradesh FR completed
7. Rajasthan-Sabarmati link Sabarmati –do– FR completed
8. Chunar-Sone Barrage

link

Ganga and Sone Bihar and Uttar Pradesh FR completed
9. Sone Dam – Southern Tributaries of Ganga link Sone and Badua Bihar and Jharkhand PFR completed
10. Ganga (Farakka)-Damodar-

Subernarekha link

Ganga, Damodar and Subernarekha West Bengal,Odisha and

Jharkhand

FR completed

DPR in progress

11. Subernarekha-Mahanadi link Subernarekha and Mahanadi West Bengal and Odisha FR completed
12. Kosi-Mechi Link Kosi and Mechi NEPAL & INDIA

(Bihar and West Bengal)

PFR completed
13. Ganga (Farakka)-Sunderbans link Ganga and

Ichhamati

West Bengal FR completed
14. Jogighopa-Tista-Farakka

link (Alternative to M-S-T-G)

Manas,Tista and Ganga Assam, Bihar and West

Bengal

PFR completed

 

 

  • PFR- Pre Feasibility Report
  • FR- Feasibility Report
  • DPR- Detailed Project Report

 