Status of Development of Waterways in India

ad
National Waterways
6-rivers-of-goa-to-be-developed-as-national-waterways-indian-bureaucracy-indianbureaucracy

Based on the outcome of techno-economic feasibility and Detailed Project Reports (DPRs) of the NWs completed, action plan has been formulated for 26 NWs which have been found viable for cargo/passenger movement. The list of the 26 NWs with their status (state-wise) is at Annex-1. Development activities have been initiated in the first 13 NWs out of these 26 NWs. Details and status of waterways of Karnataka undertaken for development is at Annex-2.

The details of targets set and expected expenditure involved for completion of waterways projects are at Annex-3.

Under National Perspective Plan (NPP) prepared in year 1980 for inter-basin water transfer, National Water Development Agency (NWDA), Ministry of Jal Shakti has identified 30 links (16 under Peninsular Component and 14 under Himalayan Component) for preparation of Feasibility Reports (FRs) under Inter-linking of Rivers Project. Detailed Project Reports (DPRs) of 8 link projects, FRs of 24 links and Pre Feasibility Reports (PFRs) of all the 30 links have been completed.

Ken-Betwa link is the first link under NPP that is ready for implementation. A tripartite agreement has been signed amongst states of MP and UP and Central Govt, for the implementation of Ken-Betwa Link project in March, 2021 in the august presence of Hon’ble Prime Minister of India. Govt. of India has approved the implementation of Ken-Betwa Link Project with an estimated cost of Rs. 44605 Cr at year 2020-21 price level and central support of Rs. 39317 Cr.  [90: 10 (Central: State) ] through a Special Purpose Vehicle viz; Ken Betwa Link Project Authority. A Gazette notification for the same has been issued by Ministry of Jal Shakti on 11.2.2022. The implementation of the link has been initiated. The funding pattern as approved by Govt. of India for Ken-Betwa Link project is applicable to Ken-Betwa Link project only.

The funding pattern and sanction of funds for any ILR project is decided on case to case basis at the time / stage of their implementation.

Annex-1

 

LIST OF 26 NATIONAL WATERWAYS FOUND FEASIBLE FOR CARGO / PASSENGER MOVEMENT

 

Sl. No National Waterway Details of Waterways STATES Status
1 National Waterway 1 Ganga-Bhagirathi-Hooghly River System (Haldia – Allahabad) Uttar Pradesh, Bihar, Jharkhand & West Bengal Development taken up with Assistance from World Bank Jal Marg Vikas Project
2 National Waterway 2 Brahmaputra River (Dhubri – Sadiya) Assam Development taken up as per approved SFC for FY 2020-21 to 2024-25
3 National Waterway 16 Barak River Assam
4 National Waterway 3 West Coast Canal (Kottapuram – Kollam), Champakara and Udyogmandal Canals Kerala Mostly Operational Waterways and development and maintenance work taken up.

 

 

5 National Waterway 4 Krishna River (Vijayawada – Muktyala) Andhra Pradesh
6 National Waterway 5 Dhamra-Paradio via Mangalagadi to Pankopal Odisha
7 National Waterway 8 Alappuzha- Changanassery Canal Kerala
8 National Waterway 9 Alappuzha – Kottayam – Athirampuzha Canal Kerala (Alternate route: 11.5km)
9 National Waterway 27 Cumberjua River Goa
10 National Waterway 68 Mandovi River Goa
11 National Waterway 86 Rupnarayan River West Bengal
12 National Waterway 97 Sunderbans Waterway West Bengal
13 National Waterway 111 Zuari River Goa
14 National Waterway 10 Amba River Maharashtra Development proposal at appraisal stage.
15 National Waterway 40 Ghagra River Bihar
16 National Waterway 44 Ichamati River West Bengal
17 National Waterway 52 Kali River Karnataka
18 National Waterway 57 Kopili River Assam
19 National Waterway 25 Chapora River Goa
20 National Waterway 37 Gandak River Bihar
21 National Waterway 28 Dabhol Creek Vasisti River Maharashtra
22 National Waterway 73 Narmada River Maharashtra & Gujarat
23 National Waterway 85 Revadanda Creek – Kundalika River System Maharashtra
24 National Waterway 94 Sone River Bihar
25 National Waterway 100 Tapi River Maharashtra & Gujarat
26 National Waterway 31 Dhansiri River Assam

 

Annex-2

Details and status of waterways of Karnataka undertaken for development:

 

Sl.No. PROJECT Cost (in Rs. Cr.)
1. Integrated Development of Tadadi-Aghanshini Waterway in Kumta Taluka of Uttar Kannada District 20
2. Development of waterways on Gurupur (NW-43) in Mangalore Taluka of Karnataka 29.62
3. Development of waterways from Hangarkatte to Manipal in Udupi Taluka of Karnataka 25
4. Development of waterways from Almatti to Bagalkot in Karnataka 12.2
5. Development of waterways on Kali river (NW-52 ) in Karwar Taluka of Karnataka (Phase-1) 14.46

 

            Out of above, in-principal approval for funding under Sagarmala Scheme has been conveyed by the Ministry for projects at Sl. No. 1, 2 & 4 above. W.r.t Sl. No. 5, an amount of Rs. 2.70 Cr.  has been released by IWAI to Govt. of Karnataka in 2021.

 

Annex.-3

The details of targets set and expected expenditure involved for completion of waterways projects:

 

Project Cost (in Cr.) Completion
National Waterway-1 (NW-1)
  • JMVP
Rs. 3887.81 Dec, 2023
  • JMVP-II (ArthGanga )
Rs. 746.00 Dec, 2023
National Waterway-2 (NW-2) Rs. 461.00 Mar, 202 5
National Waterway-16 (NW-16) Rs. 145.00 Mar, 2025

 

This information was given by the Union Minister for Ports, Shipping and Waterways, Shri Sarbananda Sonowal in a written reply to the Rajya Sabha.