Coal India facing delays in ongoing 89 projects

0
215
Coal India 89 ongoing
Coal India 89 ongoing projects -indian Bureaucracy

As many as 89 projects of Coal India are running behind schedule due to reasons such as delay in green clearances and law and order problems, the world’s largest coal miner said in a report of the 89 delayed projects, 62 are mining projects and 27 are non-mining projects, Coal India (CIL) said in the report.

Coal India has ambitious target of raising its annual production to 1 billion tonnes by 2020 from around 550 million tonnes at present.”Out of 120 (mining) coal projects, 58 projects are running on schedule and 62 are delayed,” the PSU said.

Of the 62 delayed mining projects, 34 are running behind the schedule on account of delays in getting forestry clearances and 17 are delayed because of land acquisition and associated R&R issues.”In addition, seven projects are running behind the schedule due to delay or discontinuance of work or non- participation in tender by contractor, one project due to law and order problem and three projects due to lack of railway infrastructure facilities for coal evacuation,” it said.

The non mining projects, the PSU said, are running behind schedule due to discontinuance of work by contractor, law and order problem, acquisition of land and associated problems of rehabilitation and forestry clearances.

In 2017-18, CIL has been pegged production target at 600 million tonnes (mt) with an annualised growth of about 8.3 per cent over the last year. In 2018-19, the envisaged coal production projection is 773.70 MT with a growth of about 28.95 per cent.

The company had missed the annual production target of 598.61 mt for 2016-17 by 44.48 mt.

Previous articleUS based ITBD commits employment of 200 Indian IT professionals
Next articleSteel Consumption Awareness Campaign by SAIL
Saurabh
Saurabh Sinha, Editor of IndianBureaucracy.com, is known for his credible, precise and insightful coverage of governance, civil services and administrative developments in India. Under his leadership, the portal has grown into a trusted national platform for accurate updates, appointments and policy movements within the bureaucratic ecosystem. Saurabh’s strong professional networking and deep understanding of government functioning enable him to present timely, reliable and well-contextualised information to readers across sectors. As a thought-driven editor, he promotes informed dialogue on governance reforms while maintaining high editorial standards. His calm, consistent and detail-oriented approach continues to strengthen the portal’s reputation. इंडियनब्यूरोक्रेसी.कॉम के संपादक सौरभ सिन्हा देश की नौकरशाही, शासन व्यवस्था और प्रशासनिक गतिविधियों की विश्वसनीय तथा संतुलित रिपोर्टिंग के लिए जाने जाते हैं। उनके नेतृत्व में यह पोर्टल नियुक्तियों, नीतिगत बदलावों और प्रशासनिक खबरों का एक भरोसेमंद राष्ट्रीय स्रोत बन चुका है। शासन तंत्र की गहरी समझ और मजबूत पेशेवर नेटवर्क के कारण सौरभ पाठकों को समयबद्ध, सटीक और संदर्भित जानकारी प्रदान करते हैं। एक विचारशील संपादक के रूप में वे सुशासन, पारदर्शिता और सुधारों पर सकारात्मक संवाद को बढ़ावा देते हैं। उनकी शांत, सूक्ष्म और पेशेवर संपादकीय शैली पोर्टल की प्रतिष्ठा को लगातार मजबूत कर रही है।