MoHUA and CPWD monitor all Central Vista projects on a weekly basis

0
47
Ministry of Housing and Urban Affairs
Ministry of Housing and Urban Affairs

The status and progress of various ongoing works under Central Vista Master Plan are as under:

 

Name of the Project

Amount incurred so far (₹Cr)

Physical progress

New Parliament Building

480.00

44%

Vice President Enclave

9.00

3%

Common Central Secretariat Buildings 1,2 and 3

243.00

3%

Redevelopment of Central Vista Avenue

441.00

80%

 

The total amount spent and expected to be spent on various works under Central Vista Master Plan since commencement of the work are as under:

 

Financial Year

Amount incurred / Likely to be incurred(₹Cr)

2019-20

Nil

2020-21

419.55

2021-22

1423.00 (likely expenditure)

2022-23

2285.00 (likely expenditure)

 

All the projects are monitored by Ministry of Housing and Urban Affairs and Central Public Works Department regularly on weekly basis to avoid delays and any inconvenience to general public.

 

This information was given by the Minister of State for Housing & Urban Affairs, Shri Kaushal Kishore, in a written reply in the Rajya Sabha today.