Department of Atomic Energy sets target of reaching an installed generation capacity

ad
dae-indianbureaucracy
dae-indianbureaucracy

In July 2014, a target of tripling the then existing capacity of 4780 MW in the next ten years (by 2024) was set. However, the Department of Atomic Energy (DAE) has set for itself an ambitious target of reaching an installed generation capacity of 63000 MW by the year 2031-32. A capacity of 1000 MW has already been added to the grid in December 2014 by start of commercial operation of Kudankulam Unit-1 taking the capacity to 5780 MW. The target of tripling of the capacity of 4780 MW  by 2024 is expected to be met, largely on progressive completion of projects under construction and the projects accorded financial sanction.

The Government had also accorded ‘in principle’ approval of the following sites for locating nuclear power projects in future, based on both indigenous technologies and with foreign co-operation:

Site State Capacity (MW) In cooperation with
Indigenous Reactors
Gorakhpur, Haryana 4 X 700 Indigenous
Chutka Madhya Pradesh 2 X 700
Bhimpur 4 X 700
Kaiga Karnataka 2 X 700
Mahi Banswara Rajasthan 4 X 700
With Foreign Cooperation
Kudankulam Tamil Nadu  4 X 1000 Russian Federation
Jaitapur Maharashtra  6 X 1650 France
Chhaya Mithi Virdi Gujarat   6 X 1000* USA
Kovvada Andhra Pradesh   6 X 1000* USA
Haripur West Bengal  6 X 1000 Russian Federation

*Nominal Capacity

Pre-project activities have been taken up at these sites.

Bharatiya Nabhikiya Vidyut Nigam Limited (BHAVINI), a Public Sector  Undertaking of Department of Atomic Energy (DAE) is presently constructing a Prototype Fast Breeder Reactor (PFBR) of 500 MWe capacity at Kalpakkam, Tamil Nadu.  In addition, two Fast Breeder Reactors of 600 MW are also proposed to be constructed at Kalpakkam.

A 300 MWe Advanced Heavy Water Reactor (AHWR) using Thorium based fuel has been designed and developed. This reactor will serve as a technology demonstrator for the Thorium fuel cycle technologies. A project for initiation of activities towards start of construction of AHWR has been included in the XII Plan.

The installed nuclear generation capacity by 2031-32 would depend on actual start of projects and their completion, which in turn would be contingent to completion of pre-project activities like land acquisition and obtaining statutory clearances and conclusion of techno-commercial discussion in respect of reactors to be set up with foreign co-operation.

This information was provided by MoS in the Prime Minister’s Office and Minister of State in the Ministry of Personnel, PG & Pensions, Dr Jitendra Singh in written reply to an unstarred question in the Lok Sabha.

IndianBureaucracy.com wishes the very best.

Be the first to comment

Leave a Reply