Minister of State for Shipping and Road Transport and Highways Shri Pon. Radhakrishnan  has conveyed that Master Plans have been prepared for all the 12 major ports under Sagarmala Programme, and 142 port capacity expansion projects with total cost: Rs. 91,434 Cr and capacity of 884 MTPA have been identified for implementation over the next 20 years.

The installed capacity in Major Ports is sufficient to handle the existing cargo traffic. Against the installed capacity of 1065.83 MTPA as on 31st March.3.2017, the traffic handled by the Major ports during 2016-17 was 647.76 MT.

During 2016-17, 100.47 million tonnes of capacity was added to the major ports. Port-wise capacity addition is as under:

(Million Tonnes)

S. No. Name of the Port Capacity Addition
1 Kolkata 5.11
2 Haldia 4.00
3 Paradip 16.50
4 Visakhapatnam 3.00
5 Kamarajar(Ennore) 12.00
6 Chennai 0.00
7 V.O. Chidambaranar 6.64
8 Cochin 6.91
9 New Mangalore 9.86
10 Mormugao 1.25
11 Mumbai 16.00
12 JNPT 0.00
13 Kandla 19.20
Total 100.47

 